HomeMy WebLinkAbout2022 Agreement with M&A Jones for constructionBatesville Public Works Facility
Batesville, Arkansas
AGREEMENT
ETC Project Number 2106601CBATE
THIS AGREEMENT made this O `day of October, 2022, by and between M & A Jones
Construction 1530 Batesville Blvd., Batesville AR 72501 (a corporation organized and
existing under the laws of the State of Arkansas) hereinafter called the "Contractor" and the
City of Batesville, Arkansas an agency thereof hereinafter called the "Owner".
WITNESSETH:
That the Contractor and the Owner for the consideration stated herein mutually agrees as
follows:
ARTICLE 1. Statement of Work. The Contractor shall furnish all supervision, technical
personnel, labor, materials, machinery, tools, equipment, incidentals and services, including
utility and transportation services and perform and complete all work required for "City of
Batesville Public Works Facility`, in strict accordance with the Contract Documents, as prepared
by the Engineer.
ARTICLE 2. The Contract Price is Five million One hundred Ten thousand Eighteen and
00/100ths Dollar ($5,110,018.00). The Owner will pay the contractor, because
of his performance of the Contract, for the total quantities of work performed at
the lump sum and unit prices stipulated in the Proposal, subject to additions. and
deductions as provided in the Section entitled "CHANGES IN THE WORK" under
GENERAL CONDITIONS.
ARTICLE 3. Contract Time. The Contractor agrees to begin work within ten (10) calendar
days after issuance by the Owner of a "Work Order" or "Notice to Proceed" and
to complete the work within Two Hundred Seventy (270) consecutive calendar
days thereafter (except as modified in GENERAL CONDITIONS of these
Contract Documents). If the Contractor shall fail to complete the work within the
time specified, he and his Surety shall be liable for payment to the Owner, as
liquidated damages ascertained and agreed, and not in the nature of a penalty,
the sum ofTwo HundredFifty Dollars ($250.00) for each day of delay. To the
extent sufficient in amount, liquidated damages shall be deducted from the
payments to be made under this Contract.
ARTICLE 4. Contract. The executed Contract Documents shall consist of the following
a. This Agreement
b. Exhibit-1 (5 Pages)
C. Advertisement for Bids
d. Information for Bidders
e. Bid Proposal
f. General Conditions
g. Construction Plans
h. Technical Specifications
00007-1
Batesville Public Works Facility
Batesville, Arkansas
ETC Project Number 2106601CBATE
This Agreement, together with other Documents enumerated in this Article 4, which said other
Documents are as fully a part of the Contract as if hereto attached to herein repeated, form the
Contract between the parties hereto. In the event that any provisions in any component part of
this Contract conflicts with any provision of any other component part, the conflict shall be
resolved by the Engineer whose decision shall be final.
ARTICLE 5. Surety. The Surety on the Performance -Payment Bond shall be a surety
company of financial resources satisfactory to the Owner and authorized to do business in the
State of Arkansas.
IN WITNESS WHEREOF, the parties hereto have caused this AGREEMENT to be executed in
four (4) counterparts, each of which shall be considered an original on the day and year first
above written.
(Seal)
Att
(Secretary)
(W ess)
(Seal)
Attest
0A
( ecretary)
(Witness)
By
CITY OF BATESVILLE
(Owner)
MAYOR
(Title)
M & A Jones Construction
(Contractor)
By
/" S• /" -P/
(Title)
00007-2
EXHIBIT-1
City of Batesville Public Works Facility
Value Engineering Adjustments
Date 9/30/2022
1
Office Building —go to typical Pre -Engineered Metal Building(PEMB)
-$448 097.00
2
Maintenance Building and Vehicle Storage
-$169,105.00
3
Go to 14' x 14' metal back insulated overhead doors with 6' highlift,
electric operator
-$67,095.00
4
Use alternate lighting package for the high bay fixtures in
Maintenance Building and Vehicle Storage
-$12,524.00
5
Use aluminum panel feeder conductors
-$5,656.00
6
Go to 4" vinyl back fiberglass insulation in Maintenance Building and
Vehicle Storage
-$10,430.00
7
Landscaping— use $10,000.00 Allowance
-$12,000.00
8
Delete stamped concrete between Offices and Maintenance Building
-$9 240.00
9
Delete all the trench drains in the Maintenance Building
-$84,657.00
Maintenance Building — delete two showers, add two water closets,
10
add two toilet paper dispensers
$87.00
Maintenance Building — extend two walls in M103 and M109 by 4'
11
each. Add light fixtures, glass, masonry, metal roof panels, carpentry,
ceiling, paint
$4,028.00
12
Move a/c condensing units on Office to sidewalls. Add concrete
pads and coolant lines
$1,008.00
13
Maintenance Building — move air compressor to the outside, extend
air lines, add 4' x 6' chain link enclosure with metal panel roof
$6,296.00
Vehicle Storage — add three overhead doors, delete one personnel
14
door, add electrical power, add six painted pipe bollards
$26,757.00
OFFICE — Delete safety room, delete masonry and above grade
15
concrete, change to normal entry door
-$17,680.00
Vehicle Storage — enclose wash bay
16
Add sidewalls to metal building, add two overhead doors, add four
painted pipe bollards, add electric power, add 4" fiberglass insulation
$25,157.00
17
Maintenance Building
Go to Ashford formula concrete hardener
$3,784.00
18
Maintenance Building and Vehicle Storage
Delete galvanized snow bar
-$23,236.00
19
Go to 1000 gallon sand filter in lieu of 2000 gallon
-$2,800.00
OFFICE —delete two 5A aluminum glass openings and wooden doors
20
in 0115 and 0116. Add metal studs and painted gypsum board
-$4,416.00
21
Sub Total
$866,936.00
$67,117.00
22
0'
Agreed to the attached Itamized conditions/ comments
Accepted By:
M & A Jones Construction
Contract
By. ��',
/1a_>z
Title c President Date
1 of 5
Batesville Public Works — Value Engineering and Adjustment Items
1. Office Building — go to typical Pre -Engineered Metal Building(PEMB)
- Delete structural steel, PVC roofing, polyisocyanu rate insulation, metal
trim and 16" snap clad roofing
- Delete roof drains, celestial glass
- Adjust concrete for footings
- Adjust metal studs, gypsum board, fiberglass insulation
- Add drop ceiling
- Adjust HVAC duct and grills, electrical lighting
- Delete carpentry trim, eye brows, accent wall
- Add metal building with 26 gauge PBR roof panel, 4' overhangs,
smooth soffit panels
- Use same metal siding
DEDUCT $448,097.00
Acceptable with Comments:
• Pettit & Pettit— Alternate light fixture schedule shall be submitted for
review. Must have similar lumen outputs and emergency capabilities.
Architect shall review architectural aesthetic.
• ETC - Redesign of Architectural and Structural is necessary. Roof
Gutter & Downspout with Concrete Splash Block shall be included
2. Maintenance Building and Vehicle Storage
- Go to 26 gauge 'PBR' screw down roof panels
- Go to 26 gauge 'PBR' wall panels
- Delete all roof overhangs
- Add seven 4' x 4' door awnings
DEDUCT $169,105.00
Acceptable with Comments:
• Pettit & Pettit — Adjust lighting to not be above door awnings.
• ETC - Roof Gutter & Downspout with Concrete Splash Block shall be
included.
3. Go to 14' x 14' metal back insulated overhead doors with 6' highlift,
electric operator
Acceptable.
DEDUCT $67,095.00
2of5
4. Use alternate lighting package for the high bay fixtures in Maintenance
Building and Vehicle Storage.
DEDUCT $12,524.00
Acceptable with Comments:
• Pettit & Pettit — Alternate light fixture schedule shall be submitted
for review. Must have similar lumen outputs and emergency
capabilities. Architect shall review architectural aesthetic.
5. Use aluminum panel feeder conductors.
DEDUCT $5,656.00
Acceptable with Comment:
• Pettit & Pettit — Adjust size to match ampacity of copper.
6. Go to 4" vinyl back fiberglass insulation in Maintenance Building and
Vehicle Storage.
DEDUCT $10,430.00
• Acceptable.
7. Landscaping— use $10,000.00 Allowance
DEDUCT $12,000.00
• Acceptable.
8. Delete stamped concrete between Offices and Maintenance Building.
DEDUCT $9,240.00
Acceptable with Comments:
• ETC - Replaced with 3000 PSI concrete with 6"x6" W2.9xW2.9 Wire
Mesh.
9. Delete all the trench drains in the Maintenance Building.
DEDUCT $84,657.00
• Acceptable.
10. Maintenance Building — delete two showers, add two water closets, add
two toilet paper dispensers.
ADD $87.00
Acceptable.
3of5
11. Maintenance Building — extend two walls in M103 and M109 by 4' each.
Add light fixtures, glass, masonry, metal roof panels, carpentry, ceiling,
paint.
ADD $4,028.00
Acceptable.
12. Move a/c condensing units on Office to sidewalls. Add concrete pads
and coolant lines.
ADD $1,008.00
Acceptable with Comments:
• Pettit & Pettit — Extend electrical circuits and refrigerant piping as
needed.
13. Maintenance Building — move air compressor to the outside, extend air
lines, add 4' x 6' chain link enclosure with metal panel roof.
ADD $6,296.00
Acceptable with Comments:
• Pettit & Pettit — Extend electrical circuits as needed.
14. Vehicle Storage — add three overhead doors, delete one personnel
door, add electrical power, add six painted pipe bollards.
ADD $26,757.00
Acceptable.
15. OFFICE — Delete safety room, delete masonry and above grade
concrete, change to normal entry door.
DEDUCT $17,680.00
Acceptable.
4of5
16. Vehicle Storage — enclose wash bay
- Add sidewalls to metal building, add two overhead doors, add four
painted pipe bollards, add electric power, add 4" fiberglass insulation
ADD $25,157.00
Acceptable.
17. Maintenance Building
- Go to Ashford formula concrete hardener
ADD $3,784.00
Acceptable
18. Maintenance Building and Vehicle Storage
- Delete galvanized snow bar
DEDUCT $23,236.00
Owner's Call.
19. Go to 1000 gallon sand filter in lieu of 2000 gallon.
DEDUCT $2,800.00
Acceptable.
20. OFFICE — delete two 5A aluminum glass openings and wooden doors in
0115 and 0116. Add metal studs and painted gypsum board.
DEDUCT $4,416.00
Acceptable.
September 30, 2022