HomeMy WebLinkAbout2001-06-02-R (MOO 0
Resolution No
Whereas, the Board of Commissioners of the Batesville Water Utilities,
Batesville, Arkansas, received bids on May 16, 2001, for construction of main water and
main sewer lines to the east part of the University of Arkansas Community College at
Batesville Campus; and
Whereas, the lowest and best bid was in the amount of$145,317.00 ($156,687.00
minus deductive alternate No. 1) submitted by Hargan Construction Company of
Batesville, Arkansas; and
Whereas, the scope of the project has been reduced to $112,052.85 plus
engineering and contingencies; and
Whereas, Batesville Water Utilities has remaining industrial park sewer line grant
funds of approximately $60,000.00 that must be used in this area; and
Whereas, the University of Arkansas Community College at Batesville has agreed
to pay all costs over and above $60,000.00 for construction of main water and main
sewer lines to the east portion of the University of Arkansas Community College at
Batesville campus including engineering and contingencies; and
Whereas, the City Council of the City of Batesville has requested that they be
informed of any construction to serve customers outside the city limits of the City of
Batesville; and
Whereas, the Board of Commissioners of the Batesville Water Utilities does
hereby desire to keep the City Council of the City of Batesville informed of such
construction; and
Whereas, the-Chancellor of the University of Arkansas Community College at
Batesville has begun the process of petitioning for annexation the east portion of the
campus into the City of Batesville; and
Whereas, the Board of Commissioners of the Batesville Water Utilities believe
construction of main water and main sewer lines to the east portion of the campus of the
University of Arkansas Community College at Batesville will protect the health, safety
and welfare of the inhabitants of the City of Batesville;
Now therefore, be it resolved by the City Council of the City of Batesville that the
Board of Commissioners of the Batesville Water Utilities proceed with this project.
PASSED AND APPROVED thisd,("P-day of . 2001.
CITY OF BATESVILLE
( BATESVILLE, ARKANSAS
firâ–º Attest:
Joe Biard, Mffylor
COST SHARING AGREEMENT FOR CONSTRUCTION
OF MAIN WATER AND MAIN SEWER LINE
KNOW ALL MEN BY THESE PRESENTS:
That the City of Batesville Arkansas, by and through the Batesville
Utilities Commission, an agency of the City of Batesville, hereinafter
referred to as Utilities Commission, and the University of Arkansas
Community College at Batesville, a division of the University of Arkansas,
hereinafter referred to as UACCB, have entered into an agreement regarding
payment for the construction of certain main water lines and main sewer
lines to the addition to the UACCB campus east of Pfeiffer Creek near
Batesville Arkansas, and desire to commit the terms of their agreement to
writing as follows:
1. This contract is subject to conditions precedent. The lands
which will be served by the proposed main water line and main sewer line
I
lie outside the current boundaries of, but are contiguous to, lands lying
within the boundaries of the City of Batesville, Arkansas. This contract is
contingent upon and subject to the approval by majority vote of the City
Council of Batesville, Arkansas, and upon the annexation into the Batesville
Municipal corporation boundaries of the lands owned by UACCB east of
Pfeiffer Creek which are outside the city limits, but contiguous to the present
campus of UACCB and contiguous to the present municipal boundaries of
the City of Batesville, Arkansas.
2. The Utilities Commission and UACCB shall jointly request
approval of this contract by the Batesville City Council.
3. UACCB shall use all reasonable efforts, beginning forthwith,
and shall pursue vigorously the annexation of the affected lands into the City
of Batesville, Arkansas.
4. Main water lines and main sewer lines will be constructed as
specified in a contract, as amended by change orders, between Hargan
Construction Company as contractor, and the Utilities Commission,
described as McGoodwin, Williams and Yates project number Ba-111, as
more particularly shown in specifications, contract documents, and plans for
said project.
5. The Utilities Commission shall contribute for payment of the
contract price for construction of the project by Hargan Construction
Company, engineering costs, environmental consultants costs, and fees, the
remainder of the industrial park sewer line grant monies, (Economic
Development of Arkansas Fund Commission Grant) that shall remain after
the completion of work now in progress on McGoodwin, Williams and
Yates project number Ba-97. This sum is now estimated to be
I%w
approximately $60,000.00. UACCB shall pay all other costs of the project,
including construction contract payments to Hargan Construction Company,
engineering costs, environmental consultants costs, and fees. The sums paid
by UACCB for construction contract payments shall include not only those
remaining construction costs contemplated in the Hargan Construction
Company bid, as modified, but shall include also all additional costs which
may be incurred due to unknown circumstances including but not limited to
unknown subterranean conditions such as excessive rock, garbage disposal
sites, sink holes, underground caverns, etc.
6. The Utilities Commission shall advance funds for payment as
payments shall become due to Hargan Construction Company, to the
consulting engineers, the environmental consultants, and for fees until all
funds remaining under the Economic Development of Arkansas Fund
Commission Grant mentioned in paragraph five (5) above have been
exhausted. Thereafter all payments shall be paid by UACCB to the Utilities
Commission as payments shall become due under the contract with Hargan
Construction Company, to the consulting engineers, the environmental
consultants and for fees. All payments shall be based on pay estimates as
approved by the Utilities Commission and McGoodwin, Williams and Yates,
consulting Engineers for the Utilities Commission for the project.
7. No water or sewer service shall be provided to UACCB campus
east of Pfeiffer Creek until the annexation of that portion of the campus into
the City of Batesville Arkansas is completed.
EXECUTED upon the date appearing herein below opposite the
signature of the parties hereto.
Jim Whitson, Chairman Batesville Utilities Date
Jim Reid, Secretary Batesville Utilities Date
Dr. Jack Lassiter, Chancellor Date
University of Arkansas Community College
Of Batesville
Approved by majority vote of the Batesville City Council on this 26th day of
June, 2001.
Joe Baird, Mayor
Attest:
Denise Johnson