D. Security light pole system <br /> E. Stage <br /> Phase 3 to be complete April 12017: <br /> 1) Build restroom with native stone. <br /> 2) Install security light pole system. <br /> 3) Install large tanning stone that belonged to the Maxfield family and was donated to the <br /> park. <br /> 4) Construct a concrete pathway into the green space. <br /> Phase 4 to be complete November 1, 2017: <br /> 1) Install safety fences in areas that will require them. These areas are: <br /> A. Along the north edge of the park that runs parallel to the railroad tracks. <br /> B. Along areas with a vertical elevation change or drop off. <br /> 2) Install bleachers along sloped embankment that faces the playground and Polk Bayou. <br /> Phase 5 to be complete October 1, 2017: <br /> 1) Build water fall and fish pond with a bridge crossing it. <br /> 2) Build and install the memorial fountain/ sculpture. <br /> 3) Complete landscaping. <br /> 4) Pave all areas of parking lot. <br /> Phase 6 to be complete March 15, 2019: <br /> 1) Install children's playground <br />